2257 FEDERAL-AID PROJECT RESOLUTION
RESOLUTION NO. ?'
A RESOLUTION EXPRESSING THE WILLINGNESS OF
THE CITY OF WEST MEMPHIS
TO UTILIZE FEDERAL-AID FUNDS
FOR THE FOLLOWING CITY PROJECT:
Rich Road Bridge Replacement
WHEREAS, the West Memphis Area Transportation Study has approved Federal-aid
Highway Infrastructure Program funds for the project at the following Federal and City
participating ratios, up to the maximum Federal-aid available:
Type Work Work Phase Federal % City %
Projects that reach construction Preliminary Engineering 80 20
Right-of-Way 80 20
Utilities 80 20
Construction 80 20
Construction Engineering 80 20
Projects that never progress to All Phases -0- 100
construction
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF WEST
MEMPHIS, ARKANSAS THAT:
SECTION I: The City will participate in accordance with its designated responsibilities
in this project.
SECTION II: The Mayor or his designated representative is hereby authorized and
directed to execute all appropriate agreements and contracts necessary to expedite the construction
of this City project.
SECTION III: The City pledges its full support and hereby authorizes the Arkansas
Department of Transportation to initiate action to implement this project.
THIS RESOLUTION adopted this �'� day of , 2021.
e ��---
Marco McClendon
Mayor of West Memphis
ATTEST: RECE D
(SEAL) Clerk'
D me
AGREEMENT OF UNDERSTANDING
BETWEEN
THE CITY OF WEST MEMPHIS
AND
THE ARKANSAS DEPARTMENT OF TRANSPORTATION
In Cooperation with the
U.S. Department of Transportation, Federal Highway Administration
RELATIVE TO
Implementation of the Rich Road Bridge Replacement, (hereinafter called the "Project") as a
Federal-aid Surface Highway Improvement Program project.
WHEREAS, funding in Fixing America's Surface Transportation (FAST) Act includes 80%
Federal-aid funds to be matched with 20%non-federal funds for certain city projects; and
WHEREAS, the City of West Memphis (hereinafter called "Sponsor") has expressed its desire
to use Federal-aid funds for the eligible Project and to provide necessary matching cash share for
such funds; and
WHEREAS, the Sponsor will transmit to the Arkansas Department of Transportation(hereinafter
called the "Department") a signed and sealed Resolution from the City Council authorizing the
Mayor to execute agreements and contracts with the Department for the Project; and
WHEREAS, funding participation will be as follows, subject to the amount of Federal-aid funds
and obligation limitation approved and available for the Project:
Maximum Minimum
Federal % Sponsor%
Preliminary Engineering by Consultant 80 20
Right-of-Way/Utilities 80 20
Construction 80 20
Construction Engineering by Consultant 80 20
Department Administrative Costs 80 20
WHEREAS, the Sponsor knows of no legal impediments to the completion of the Project; and
WHEREAS, it is understood that the Sponsor and the Department will adhere to the General
Requirements for Recipients and Sub-Recipients Concerning Disadvantaged Business Enterprises
(DBEs)(Attachment A*)and that,as part of these requirements,the Department may set goals for
DBE participation in the Project, ranging from 0% to 100%, that are practical and related to the
potential availability of DBEs in desired areas of expertise.
WHEREAS, the Department has published the Arkansas Local Public Agency Project Manual
(available at www.ardot.gov/LPA) which outlines procedures and requirements which must be
followed during development and construction of the Project; and
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
WHEREAS, the parties agree, unless specifically stated otherwise, that the provisions of this
agreement are not intended to create or confer a third party benefit or right in any person or entity,
not a party to this agreement.
IT IS HEREBY AGREED that the Sponsor and the Department, in cooperation with the Federal
Highway Administration (FHWA), will participate in a cooperative program for implementation
and will accept the responsibilities and assigned duties as described hereinafter.
THE SPONSOR WILL:
1. Initially submit to the Department $1,000 (20%) to be matched by $4,000 (80%) Federal-aid
funds for Department administrative costs associated with state preliminary engineering,
which include but are not limited to, on site meetings, environmental review, and plan and
specification review. The Sponsor's final cost for this phase will be determined by actual
Department charges to preliminary engineering.
2. Be responsible for hiring a consultant engineering firm(s)in accordance with the Local Agency
Consultant Selection Procedures (Attachment B*) to provide engineering services which
include environmental documentation, preliminary engineering, and construction engineering
for the Project. NOTE: FHWA authorization and Department approval must be given
prior to issuing a work order to the consultant for federal funds to be allowed in this
phase.
3. Prepare plans, specifications, and a cost estimate for construction. A registered professional
engineer must sign the plans and specifications for the Project. (See Attachment C* for items
to be included in the bid proposal.)
4. Make periodic payments to the consultant for preliminary engineering for the Project and
request reimbursement from the Department. Reimbursement requests should be submitted,
at minimum, every three (3) months and not more than once per month.
5. Understand that expenditures for preliminary or construction engineering performed by
the Sponsor's forces are not eligible for reimbursement with federal funds.
6. Prepare the necessary environmental documentation as required by FHWA and conduct any
required public involvement meetings and public hearings.
7. Ensure that the plans and specifications are developed using the Department's standard
drawings and Standard Specifications for Highway Construction(latest edition).
8. Ensure that the plans and specifications comply with the Americans with Disabilities Act
(ADA),the American Association of State Highway and Transportation Officials (AASHTO)
design standards, and all other applicable state and federal regulations, including airport
clearance when necessary, for the type of work involved.
9. Before acquiring property or relocating utilities, contact the Department's Right of Way
Division to obtain the procedures for acquiring right-of-way and adjusting utilities in
compliance with federal regulations. NOTE: Failure to notify the Department prior to
initiating these phases of work may result in all project expenditures being declared non-
participating in federal funds.
-2-
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
10. Acquire property in accordance with the Uniform Relocation Assistance and Real Property
Acquisition Policies Act of 1970, as amended (commonly referred to as the "Uniform Act").
11. Ensure the preparation of utility adjustment and right-of-way plans are in accordance with
Arkansas State Highway Commission Policy.
12. Provide a copy of the registered deed or other approved documentation and an appropriate
certification stating the Sponsor's clear and unencumbered title to any right-of-way to be used
for the Project(See Attachment D*). NOTE: Any property that is to become Department
right-of-way must be acquired in the Department's name.
13. Submit plans at 30%, 60%, and 90% completion stages for Department review.
14. Submit a certification letter (Attachment E*), including all items noted, to the Department
when requesting authority to advertise the Projects for construction bids.
15. Advertise for bids in accordance with federal procedures as shown in Attachment F*. NOTE:
FHWA authorization and Department approval must be given prior to advertising for
construction bids.
16. Forward a copy of all addenda issued for the Project during the advertisement to the
Department.
17. After bids are opened and reviewed, submit a Certification Letter Requesting Concurrence in
Award (Attachment G*), including all items noted, to the Department.
18. Prior to awarding the construction contract,submit a check for$1,000 to be matched by$4,000
(80%) Federal-aid funds for Department administrative costs on the Project during
construction. The Sponsor's final share of cost for this phase will be determined by actual
Department charges to construction engineering.
19. Notify the Department in writing who the Sponsor designates as its full-time employee to be
in responsible charge of the day to day oversight of the Project (Attachment H*). The duties
and functions of this person are:
• Oversee project activities, including those dealing with cost, time, adherence to contract
requirements, construction quality and scope of Federal-aid projects;
• Maintains familiarity of day to day project operations, including project safety issues;
• Makes or participates in decisions about changed conditions or scope changes that require
change orders and/or supplemental agreements;
• During construction, visits and reviews the project on a daily basis;
• Reviews financial processes, transactions and documentation to ensure that safeguards are
in place to minimize fraud, waste, and abuse;
• Directs project staff, Sponsor or consultant,to carry out project administration and contract
oversight, including proper documentation;
• Be aware of the qualifications,assignments and on-the-job performance of the Sponsor and
consultant staff at all stages of the project.
20. Prior to issuing the notice to proceed to the Contractor, hold a pre-construction meeting with
the Contractor and invite the Department's Resident Engineer assigned to the Project.
-3-
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
21. Ensure that all work, material testing and acceptance, and inspection is conducted in
accordance with the Department's Standard Specifications for Highway Construction (latest
edition), Manual of Field Sampling and Testing Procedures, and Resident Engineer's Manual
and with the plans, specifications, and all other applicable FHWA and Department procedures
for the Project.
22. Make periodic payments to the consultant for construction engineering for the Project and
request reimbursement from the Department. Reimbursement requests should be submitted,
at minimum, every three (3) months and not more than once per month.
23. Make payments to the contractor for work accomplished in accordance with the plans and
specifications and then request reimbursement from the Department on the Construction
Certification and Reimbursement Request (CCRR) form (Attachment I*). Reimbursement
requests should be submitted, at minimum, every three (3)months and not more than once per
month.
24. Attach LPA Report of Daily Work Performed (Attachment J*) for all days that correspond with
each CCRR submittal.
25. Prior to executing the work, submit construction contract change orders to the Department's
Resident Engineer in charge of reimbursements for review and approval.
26. Upon completion of the Project,hold a final acceptance meeting for the Project and submit the
LPA Final Acceptance Report form certifying that the Project was accomplished in accordance
with the plans and specifications(Attachment K*). This form must be signed by the engineer
performing construction inspection on the Project, the Department's Resident Engineer
assigned to the project, the Sponsor's full-time employee in responsible charge, and the
Sponsor's Mayor.
27. Maintain accounting records to adequately support reimbursement with Federal-aid funds and
be responsible for the inspection, measurement and documentation of pay items, and
certification of all work in accordance with the plans and specifications for the Project and for
monitoring the Contractor and subcontractor(s) for compliance with the provisions of FHWA-
1273, Required Contract Provisions, Federal-aid Construction Contracts, and Supplements.
28. Pay all unpaid claims for all materials, labor,and supplies entered into contingent or incidental
to the construction of said work or used in the course of said work including but not limited to
materials, labor, and supplies described in and provided for in Act Nos. 65 and 368 of 1929,
Act No. 82 of 1935, and Acts amendatory thereof.
29. Agree that any and all claims for damages to property or injury to persons caused by any act
or omission,negligence, or misconduct from the performance of work by the City's contractor
on the Project shall be the sole responsibility of the City's contractor and in this regard the City
shall require the contractor on the Project to procure and maintain a General Public Liability
Insurance Policy during the duration of the Project which shall be endorsed to include broad
form general liability and complete operations coverage on the Project. The contractor shall
furnish the City with documentation of proof of liability insurance coverage with submission
of the signed contract.
-4-
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
30. Agree that any claims, liability, costs, expenses, demands, settlements, or judgments arising
from misconduct or the negligent acts or omissions of the City, its employees, agents or
contractors in the performance of the Project and this Agreement must be presented to the City.
Further,the City by acceptance of this grant,agrees that the Department and the Arkansas State
Highway Commission,as the pass-through entity,have no duty or responsibility for the design,
construction, maintenance or operation of the Project that is the subject of this grant, and,
therefore shall have no liability related to the design, construction, maintenance or operation
of the Project. The City also agrees to assume all risks associated with the work to be
performed by its agents, employees, and contractors under this grant and Agreement and the
Department and the Arkansas State Highway Commission,as the pass-through entity,shall not
be responsible or liable for any damages whatsoever from the actions of the City, its
employees, agents and contractors.
31. Assure that its policies and practices with regard to its employees, any part of whose
compensation is reimbursed from federal funds, will be without regard to race, color, religion,
sex,national origin,age,or disability in compliance with the Civil Rights Act of 1964,the Age
Discrimination in Employment Act of 1967, The Americans with Disabilities Act of 1990, as
amended, and Title 49 of the Code of Federal Regulations Part 21 (49 CFR 21),
Nondiscrimination in Federally-Assisted Programs of the Department of Transportation.
32. Retain all records relating to inspection and certification, the Contractor's billing statements,
and any other files necessary to document the performance and completion of the work in
accordance with requirements of 2 CFR Part 200 — Uniform Administrative Requirements,
Cost Principles, and Audit Requirements for Federal Awards (Attachment L*).
33. Grant the right of access to the Sponsor's records pertinent to the Project and the right to audit
by the Department and Federal Highway Administration officials.
34. Be responsible for 100% of all project costs incurred should the Project not be completed as
specified.
35. Be responsible for 100%of any and all expenditures which may be declared non-participating
in federal funds, including any such award by the State Claims Commission.
36. Sign and transmit to the Department the Certification for Grants, Loans, and Cooperative
Agreements(Attachment M*), which is necessary for Project participation.
37. Repay to the Department the federal share of the cost of any portion of the Project if, for any
reason, federal participation is removed due to actions or inactions of the Sponsor, its agents,
its employees, or its assigns or the Sponsor's consultants or contractors or their agents. Such
actions or inactions shall include,but are not limited to, federal non-participation arising from
problems with design plans, specifications, construction, change orders, construction
inspection, or contractor payment procedures. The Sponsor understands and agrees that the
Department may cause necessary funds to be withheld from the Sponsor 's Motor Fuel Tax
allotment should the Sponsor fail to pay to the Department any required funds,fail to complete
the Project as specified, or fail to adequately maintain or operate the Project.
38. Be responsible for all costs not provided by the Federal Highway Administration.
39. Repay to the Department the federal share of the cost of this project if for any reason the
Federal Highway Administration removes federal participation.
-5-
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
40. Retain total, direct control over the Project throughout the life of all project improvements
outside of the Department's right-of-way and not, without prior approval from the
Department:
• sell, transfer, or otherwise abandon any portion of the Project;
• change the intended use of the Project;
• make significant alterations to any improvements constructed with Federal-aid funds; or
• cease maintenance or operation of a project due to the Project's obsolescence.
41. Be responsible for satisfactory maintenance and operation of all improvements and for
adopting regulations and ordinances as necessary to ensure this. Failure to adequately maintain
and operate the Project in accordance with Federal-aid requirements may result in the
Sponsor's repayment of federal funds and may result in withholding all future Federal-aid.
42. Submit to the Department a Single Audit in accordance with the Office of Management and
Budget(OMB) Circular A-133 each fiscal year that the Sponsor expends more than $500,000
of Federal-aid from any federal source including, but not limited to, the U.S. Department of
Transportation. The fiscal year used for the reporting is based on the Sponsor's fiscal year.
The $500,000 threshold is subject to change after OMB periodic reviews.
43. Make no alterations to the improvements constructed with Federal-aid funds without first
consulting with the Department.
44. Promptly notify the Department if the Project improvements outside of the Department's right-
of-way are rendered unfit for continued use by natural disaster or other cause.
45. Complete and transmit to the Department both pages of the Federal Funding Accountability
and Transparency Act(FFATA) Reporting Requirements (Attachment N*).
THE DEPARTMENT WILL:
1. Maintain an administrative file for the project and be responsible for administering Federal-
aid funds.
2. Review environmental documentation as prepared by the Sponsor.
3. Review plans and specifications submitted by the Sponsor.
4. Notify the Sponsor when right-of-way and/or utility plans are approved and the Sponsor may
proceed with right-of-way acquisition and/or utility adjustments.
5. Upon receipt of the Sponsor's certification of right-of-way (property) ownership, provide the
appropriate documentation to the file.
6. Ensure substantial compliance with federal contracting requirements through review of the
bidding proposal for inclusion of required federal forms, review of the administration of the
DBE program provisions, and general compliance with 23 CFR 635.
7. Advise the Sponsor when to proceed with advertisement of the Project for construction bids.
8. Review bid tabulations and concur in award of the construction contract for the Project.
-6-
Agreement of Understanding Between the City of West Memphis
and the Arkansas Department of Transportation
9. Ensure that the Sponsor and the Sponsor's consultant provide adequate supervision and
inspection of the Project by performing periodic inspections with the Sponsor's representatives
and their consultant to verify that the work being performed by the Sponsor's contractor, and
documented and certified by the Sponsor, meets the requirements of the Project plans,
specifications,and all applicable FHWA and Department procedures. The Department intends
to perform these inspections,at a minimum,when the construction work is approximately 10%
and 50%completed. The Department will also participate in the final inspection of the Project.
10. Review and approve any necessary change orders for project/program eligibility.
11. Reimburse the Sponsor 80%(Federal-aid share) for eligible construction costs approved in the
CCRR form (Attachment I*). This reimbursement will be limited to the maximum Federal-
aid amount and to the federal amount available at the time payment is requested. If the payment
requested exceeds the Federal-aid available at the time, the difference will be reimbursed as
additional Federal-aid for the Project becomes available.
12. Subject to the availability of Federal-aid allocated for the Project, pay the Sponsor the
remaining amount due upon completion of the Project and submittal of the certified LPA Final
Acceptance Report form(Attachment K*).
13. Be reimbursed for costs involved in performing all the services listed above.
-7-
A� ARKANSAS DEPARTMENT OF TRANSPORTATION
A t7OF
, ARDOT.gov IDriveArkansas.com Lorie H.Tudor, P.E., Director
KANSAS DEPARTMENT 10324 Interstate 30 1 P.O.Box 22611 Little Rock,AR 72203-2261
TRANSPORTATION Phone:501.569.2000 1 Voice/TTY 7111 Fax:501.569.2400
June 23, 2021
The Honorable Marco McClendon
Mayor of West Memphis
P.O. Box 1728
West Memphis, AR 72301
Re: Rich Road Bridge Replacement
Dear Mayor McClendon:
Reference is made to your letter requesting that the Department begin project development
on the Rich Road Bridge Replacement project recently approved by the West Memphis Area
Transportation Study.
In order to proceed with a Federal-aid project, your City Council must adopt a resolution
(sample enclosed)authorizing you to enter into any necessary agreements with the Department for
the project. Then you and the City Attorney must sign the enclosed Agreement of Understanding.
Upon receipt of the resolution and Agreement, State and Federal-aid job numbers will be assigned
and a copy of the executed Agreement of Understanding will be returned to you. When submitting
the Agreement to the Department for execution, please include the completed Attachment H,
signed Attachment M, and completed Attachment N.
If you have any questions, please contact Carlos Meredith in our Program Management
Division at(501) 569-2481 or Carlos.Meredith@ardot.gov.
Sincerely,
Jared D. Wiley
Assistant Chief Engineer—Planning
Enclosures
c: Deputy Director and Chief Engineer
Consultant Contracts Administrator
Program Management
Roadway Design
Transportation Planning and Policy
District 1
Ms. Amanda Hicks, WMATS, Study Director