Airport 05/16/13 AX-1o40 . MAIL Airport Meeting Highlights Thursday, May 16, 2013 2:50 PM From: "LYNDA AVERY" <every airport@gmad.com> To: "Lorraine Robinson" <robtoson.lorrame@sbcglobal net> Good morning, Lorraine - We missed you at the meeting. However, it was very brief. Here are a few highlights: The Runway Rehab Project is moving forward on schedule: • Pavement and underlying soil is being removed. • The schedule anticipates having the runway completed mid- July. • The contractor will then begin taxiway reconstruction. • The entire project has a projected completion date of mid-October. Let me know if you have any questions. Thanks, Lynda