We missed you at the meeting. However, it was very brief. Here are a few highlights:
The Runway Rehab Project is moving forward on schedule:
• Pavement and underlying soil is being removed.
• The schedule anticipates having the runway completed mid- July.
• The contractor will then begin taxiway reconstruction.
• The entire project has a projected completion date of mid-October.
Let me know if you have any questions.